International Journal of BIM and Engineering Science

Journal DOI

https://doi.org/10.54216/IJBES

Submit Your Paper

2571-1075ISSN (Online)

Volume 6 , Issue 1 , PP: 74-95, 2023 | Cite this article as | XML | Html | PDF | Full Length Article

Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study

Taher Salamah 1 * , Abdussalam Shibani 2 , Kheder Alothman 3

  • 1 Building Information Modeling and Management Master Programme, Syrian Virtual University - (Taher_168397@svuonline.com)
  • 2 Assistant professor in construction and project management, school of energy, construction and environment, Coventry university, Coventry, united kingdom. - (ab1732@coventry.ac.uk)
  • 3 Building Information Modeling and Management Master Programme, Syrian Virtual University - (kheder_173111@svuonline.org)
  • Doi: https://doi.org/10.54216/IJBES.060105

    Received: June 24, 2022 Accepted: January 25, 2023
    Abstract

    The Construction sector in Syria is adversely far beyond other industries in terms of economic growth rate and technological advancements, in what makes AEC projects less committed to schedule, cost, and quality. Yet, there aren’t binding criteria that stakeholders, such as contractors, and design and implementation firms might adhere to. This study explores the performance of implementing construction projects to establish a methodology to enhance schedule and cost performance through the use of Earned Value Management System (EVMS) and Building Information Modelling (BIM). This research will be key in determining key mechanisms and approaches in regards to AEC project management to improve project performance and achieve optimal efficiency regarding cost, schedule, and scope of the projects. A case study will be conducted through stages, starting with redoing the project using BIM; then using EVMS to track the schedule of the project; and finally ending with a comparison between the traditional methodology. The study suggests new methodology to the AEC projects in Syria to enhance cost and schedule performance, in addition to quantity surveying, using the EVMS and BIM. This study will constitute a cornerstone for researchers to enhance construction project management practices by using EVMS and BIM, for it is a new field of research in Syria that will help decision makers in the AEC industry to adopt a new methodology that improves upon the construction sector situation. Finally, this study will pave the way to contribute in the establishment of BIM standards and EVMS guidelines.

    Keywords :

    Earned Value Management System (EVMS) , Building Information Modelling (BIM) , Cost performance , Schedule performance , Project Controls , Primavera P6 , Autodesk Revit

    References

    [1] Alsehaimi, A., & A., Koskela, L. (2011). Improving project Management practice in the Arabian Gulf Countries by means of Lean Construction Techniques. 3ed Saudi Project Management Conference, SES, Riyadh, KSA.

    [2] Shaaban, M. (2012). Modern Project Management Using Earned Value: Theory and Application. Institute of Public Administration. Riyad, Saudi Arabia.

    [3] Bosnenah, A. M. (2011). Delay studies in Construction Projects. Ph.D. Thesis in Business Administration, Project Management Department. Arab British Academy for Higher Education, Libya, P:96.

    [4] Abdul Rahman, H. (1993). The management and cost of quality for civil engineering projects. A thesis submitted for the degree of Doctor of Philosophy Engineering, University of Manchester, Institute of Science & Technology, UK.

    [5] Morris, P., & Hough, G. (1979). The Anatomy of Major Projects, A study of the Reality of Project management. John Wiley & Sons, UK.

    [6] El- Sayegh, S. (2008). Risk assessment and allocation in the UAE construction industry. International Journal of Project Management 26, PP: 431-438.

    [7] Enshassi, A., and Abu Mosa, J. (2008). Risk Management in Building Projects: Owners’ Perspective. The Islamic University Journal, Series of Natural Studies and Engineering, Vol.16, No. 1, ISSN 1726-6807, PP: 95-123. Available at: http://www.iugaza.edu.ps/ara/research/

    [8] Kartam, N., & Kartam, S. (2001).Risk and its management in the Kuwaiti construction industry: a contractors' perspective. International Journal of Project Management 19, PP: 325-335.

    [9] Hamada, M. (2012). Construction Phase Risk Management in Syria. Damascus University Journal for Engineering Science. 28 (1). pp: 129-150.

    [10] Ez Eddien, B. (1990). Construction Project Management 2nd Edition. Translated by Institute of Public Administration for Research. The Kingdom of Saudi Arabia.

    [11] Zou, P., et al. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management 25, PP: 601-614.

    [12] Ahmed. S., Hasan, B., Jarad, F., & Dlask, P. (2016). Analyzing the change orders impact on building projects. Journal of Engineering and Applied Sciences 11(7): 1532-1537.

    [13] Roumieh, D. (1997). Factors Affecting Engineering Projects Cost and Schedule Overruns in Syria. Faculty of Civil Engineering, Construction Management Department, Al-Baath University. Pp: 6-9, 25-34.

    [14] Samer, I., Ali, J., & Hamza, A. (2005). A study of Random Factors Effects on Building Works Planning. Tishreen University Journal of Research and Scientific Studies. Engineering Sciences Series. 27 (3). pp: 141.

    [15] Syrian Prime Ministry, Higher Committee of Scientific Research. (2010). Initial Draft of the National Policy for Scientific Research and Technological Development in the Construction Sector in Syria. pp:5-9.

    [16] Qusai, S., Nasr Eddin, Kh., & Muhammed, J. (2006). Construction project Quality Management in Syria. Damascus University Journal for Engineering Science. 22 (1). Pp:9-36.

    [17] Ahmed, S., Dlask, P., Hassan, B., & Beshara, M. (2019). Pre-cast Concrete, a Key Option for the Reconstruction Phase after War, Procedia Engineering, Volume 196, Pages 211-219, ISSN 1877-7058, https://doi.org/10.1016/j.proeng.2017.08.074. (https://www.sciencedirect.com/science/article/pii/S1877705817332058) .

    [18] Ahmed, S. & Dlask, P. (2018). The Gradual Transition to BIM in Syrian Companies. Creative Construction Conference 2018, CCC 2018, Ljubljana, Slovenia.

    [19] Roumieh, N. & Ahmed, S. (2022). Adopting Risk Management Professional Methodologies as an Effective Strategy to Protect Heritage Sites in Syria, International Journal of BIM and Engineering Science, Vol. 5, No. 1, pp: 61-72.

    [20] Ahmed, S., Dlask, P., Selim, O. & Elhendawi, A. (2018). BIM Performance Improvement Framework for Syrian AEC Companies. International Journal of BIM and Engineering Science, 1(1).

    [21] Evans, M., Farrell, P., Elbeltagi, E., Mashali, A. & Elhendawi, A. (2020). Influence of partnering agreements associated with BIM adoption on stakeholder's behaviour in construction mega-projects. International Journal of BIM and Engineering Science, 3(1), pp.1-20.

    [22] Shaban, M.H. and Elhendawi, A. (2018). Building Information Modeling in Syria: Obstacles and Requirements for Implementation. International Journal of BIM and Engineering Science, 1(1).

    [23] Safour, R., Ahmed, S. & Zaarour, B. (2021). BIM Adoption around the World. International Journal of BIM and Engineering Science, 4(2), pp. 49-63.

    [24] Elhendawi, A.I.N. (2018). Methodology for BIM Implementation in KSA in AEC Industry. Master of Science MSc in Construction Project Management, Edinburgh Napier University, UK.

    [25] Salami, H., & Alothman, K. (2022). Engineering Training and its Importance for Building Information Modelling. International Journal of BIM and Engineering Science, 5(1), pp. 41-60.

    [26] Lepkova, N., Maya, R., Ahmed, S., & Šarka, V. (2019). BIM Implementation Maturity Level and Proposed Approach for the Upgrade in Lithuania, International Journal of BIM and Engineering Science, 2(1). pp: 22-38 (Doi: https://doi.org/10.54216/IJBES.020102)

    [27] Elhendawi, A., Smith, A. & Elbeltagi, E. (2019). Methodology for BIM implementation in the Kingdom of Saudi Arabia. International Journal of BIM and Engineering Science, 2(1).

    [28] Elhendawi, A., Omar, H., Elbeltagi, E. & Smith, A. (2019). Practical approach for paving the way to motivate BIM non-users to adopt BIM. International Journal of BIM and Engineering Science, 2(2).

    [29] Saada, M. & Aslan, H. (2022). The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war, International Journal of BIM and Engineering Science, 5(2), pp: 08-18.

    [30] Elgendi, A.F., Elhendawi, A., Youssef, W.M.M. & Darwish, A.S. (2021). The Vulnerability of the Construction Ergonomics to Covid-19 and Its Probability Impact in Combating the Virus. International Journal of BIM and Engineering Science, 4(1).

    [31] Banawi, A., Aljobaly, O. & Ahiable, C. (2019). A Comparative Review of Building Information Modeling Frameworks. International Journal of BIM and Engineering Science, 2(2), pp.23-49.

    [32] Yusof, N.A., Ishak, S.M. & Doheim, R. (2018). An exploratory study of building information modelling maturity in the construction Industry. International Journal of BIM and Engineering Science, 1(1), pp.6-19.

    [33] Amino, A. & Ahmed, S. (2022). Proposing a methodology to measure and develop BIM maturity in Syria, International Journal of BIM and Engineering Science, 5(1), pp: 73-89.

    [34] Dalloul, F and Saoud, L. (2023). Proposing a framework for introducing the concept of engineering digitization to develop curricula: case study - Tishreen University, Faculty of Civil Engineering, International Journal of BIM and Engineering Science, 6(1), pp: 34-51. Doi: https://doi.org/10.54216/IJBES.060103).

    [35] PMI. (2013). A Guide to the Project Management Body of Knowledge (PMBOK@Guide). Project Management Institute.

    [36] Vanhoucke M. (2012). Project Management with Dynamic Scheduling. Earned Value Management. Berlin Heidelberg: Springer-Verlag. pp.215-238.

    [37] Priyo, M. (2021). Earned Value Management System in Indonesian Construction Projects. International Journal of Integrated Engineering, 13(3), 37–45. Retrieved from https://publisher.uthm.edu.my/ojs/index.php/ijie/article/view/7179

    [38] Bhosekar S. K. & Vyas G. (2012). Cost is controlling using earned value analysis in construction industries. International Journal of Engineering and Innovative Technology, 1(4), 324-332.

    [39] Gupta R. (2014). Earned value management system. International Journal of Emerging Engineering Research and Technology, 2(4), 160-165.

    [40] Chin Keng, T., & Shahdan, N. (2015). THE APPLICATION OF EARNED VALUE MANAGEMENT (EVM) IN CONSTRUCTION PROJECT MANAGEMENT. Journal of Technology Management and Business, 2(2). Retrieved from https://penerbit.uthm.edu.my/ojs/index.php/jtmb/article/view/1096.

    [41] Mahdi, Ibrahim & Abd-Elrashed, Ibrahim & Essawy, Ahmed & Raed, Lamisse. (2018). DIFFICULTIES OF IMPLEMENTING EARNED VALUE MANAGEMENT IN CONSTRUCTION SECTOR IN EGYPT. 5.

    [42] Netto, J. T., de Oliveira, N. L. F., Freitas, A. P. A., & dos Santos, J. A. N. (2020). Critical factors and Benefits in the use of Earned Value Management in construction. Brazilian Journal of Operations & Production Management, 17(1), 1–10. https://doi.org/10.14488/BJOPM.2020.007.

    [43] Mayo-Alvarez, Luis & Alvarez-Risco, Aldo & Del-Aguila-Arcentales, Shyla & Sekar, Chandra & Yáñez, Jaime. (2022). A Systematic Review of Earned Value Management Methods for Monitoring and Control of Project Schedule Performance: An AHP Approach. Sustainability. 14. 15259. 10.3390/su142215259.

    [44] Akpanebu, J.I. (2023). Assessing the Effect of Planning on Construction Project of AKS Poly Consult Services Ltd., An MSc. Thesis Presented to the Federal University of Technology, Owerri, Nigeria, pp. 32

    [45] Jrade, A., and Lessard, J. (2015). An Integrated BIM System to Track the Time and Cost of Construction Projects: A Case Study. Journal of Construction Engineering, Volume 2015, Article ID 579486, Canada, PP: 1-10. DOI: http://dx.doi.org/10.1155/2015/579486.

    [46] Cárdenas, C., Zapata, P., & Lozano, N. (2018). Building Information Modeling 5D and Earned Value Management methodologies integration through a computational tool. Revista Ingeniería de Construcción (RIC), 33 (3). Colombia, PP: 263-278.

    [47] Sun, Ch., Man, Q., & Wang, Y. (2015). Study on BIM-based construction project cost and schedule risk early warning. Journal of Intelligent & Fuzzy Systems, China, PP: 469-477.

    Cite This Article As :
    Salamah, Taher. , Shibani, Abdussalam. , Alothman, Kheder. Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study. International Journal of BIM and Engineering Science, vol. , no. , 2023, pp. 74-95. DOI: https://doi.org/10.54216/IJBES.060105
    Salamah, T. Shibani, A. Alothman, K. (2023). Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study. International Journal of BIM and Engineering Science, (), 74-95. DOI: https://doi.org/10.54216/IJBES.060105
    Salamah, Taher. Shibani, Abdussalam. Alothman, Kheder. Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study. International Journal of BIM and Engineering Science , no. (2023): 74-95. DOI: https://doi.org/10.54216/IJBES.060105
    Salamah, T. , Shibani, A. , Alothman, K. (2023) . Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study. International Journal of BIM and Engineering Science , () , 74-95 . DOI: https://doi.org/10.54216/IJBES.060105
    Salamah T. , Shibani A. , Alothman K. [2023]. Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study. International Journal of BIM and Engineering Science. (): 74-95. DOI: https://doi.org/10.54216/IJBES.060105
    Salamah, T. Shibani, A. Alothman, K. "Improving AEC Project Performance in Syria Through the Integration of Earned Value Management System and Building Information Modelling: A Case Study," International Journal of BIM and Engineering Science, vol. , no. , pp. 74-95, 2023. DOI: https://doi.org/10.54216/IJBES.060105