Volume 5 , Issue 2 , PP: 08-18, 2022 | Cite this article as | XML | Html | PDF | Full Length Article

The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war

Michel Saada 1 * , Hala Aslan 2

  • 1 Mastering in Building Information Modeling and Management BIMM program – Syrian Virtual University, Syria - (michel_168367@svuonline.org)
  • 2 Expert rehabilitation of cultural heritage – Lecturer at Syrian Virtual University – ICOMOS Expert (International Council of Monuments and Sites), (UNESCO "A" organization) - (halaasslan2004@yahoo.fr)
  • Doi: https://doi.org/10.54216/IJBES.050201

    Received: April 18, 2022 Accepted: August 11, 2022
    Abstract

    Public facilities rehabilitation projects are the most discussed projects among humanitarian organizations working in Syria in the field of post-war rehabilitation. Since education is a basic right for every child, there is an urgent need for school rehabilitation projects, especially after the massive destruction caused by the war in Syria in the past decade. BIM technology has been used in the past years because it is an integrated and effective process for planning, studying, and implementing projects. However, BIM has not been properly used in the study of post-war rehabilitation projects, especially in developing countries. This research discusses the effectiveness of applying BIM in the rehabilitation projects of public facilities in Syria after the war by increasing the accuracy of quantities estimation for these projects. The main results indicate that the application of BIM in the Al-Ejref school rehabilitation project in the Al Qunaitra governorate represents great potential in increasing the accuracy of quantity estimation, as the traditional methods are limited and have a large margin of error.

    Keywords :

    Rehabilitation , public facilities , post-war , Quantitative estimation using BIM , Syria , Schools

    References

    [1]  Ministry  of  Education.  (22/10/2019).  Details  of  the  Ministry  of  Education's  plan  to 

    rehabilitate  damaged  schools.  Retrieved  date  11/12/2022,  from 

    http://www.pministry.gov.sy/contents/15264/%D8%AA%D9%81%D8%A7%D8%B5%D9

    %8A%D9%84-%D8%AE%D8%B7%D8%A9-%D9%88%D8%B2%D8%A7%D8%B1%D8%A9-%D8%A7%D9%84%D8%AA%D8%B1%D8%A8%D9%8A%D8%A9-%D9%84%D8%A5%D8%B9%D8%A7%D8%AF%D8%A9-%D8%AA%D8%A3%D9%87%D9%8A%D9%84-%D8%A7%D9%84%D 

    [2]  Ministry of Health. (2019). Health Statistical Bulletin. Damascus, Syria: Ministry of Health.

    [3]  PAS  1192-2.  (2013).  Specification  for  information  management  for  the  capital/delivery 

    phase of construction projects using building information modelling. UK: British Standards 

    Institution.

    [4]  BS  EN  ISO  19650-2.  (2019).  Information  management  using  building  information 

    modelling: Delivery phase of the assets. UK: The British Standards Institution.

    [5]  Yusof, N., Ishak, S. & Doheim, R., 2018. An  Exploratory Study of Building Information 

    Modelling  Maturity  in  the  Construction  Industry.  International  Journal  of  BIM  and 

    Engineering Science, 1(1), pp. 6-19.

    [6]  Elhendawi, A., 2018. Methodology for BIM Implementation in KSA in AEC Industry. Master 

    of Science MSc in Construction Project Management ed. Edinburgh, UK: Edinburgh Napier 

    University, UK.

    [7]  Shaban, M. & Elhendawi, A., 2018. Building Information Modeling in Syria: Obstacles and 

    Requirements for Implementation.  International Journal of BIM and Engineering Science, 

    1(1), pp. 42-64. 

    [8]  Salami, H. & Alothman, K., 2022. Engineering Training and its Importance for Building 

    Information Modelling. International Journal of BIM and Engineering Science, 5(1), pp. 41 -60.

    [9]  Pedro, J. B. (2008).  LNEC's  collaboration in the analysis of the habitability conditions of 

    buildings in Bairro do Alto da Cova da Moura. Rehabilitation needs assessment method. 

    Conception, experimental application and training of technical evaluators. Lisbon, Portugal: 

    The Laboratório Nacional de Engenharia Civil.

    [10]  Ahmed, S., Dlask, P., & Hassan, B., Improvement and innovation in the management of 

    change  orders,  Journal  of  Engineering  and  Applied  Sciences,  2018.  DOI: 

    10.3923/jeasci.2018.7975.7979. 

    [11]  Ahmed, S., Dlask, P., Hassan, B., & Beshara, M., Pre-Cast Concrete, a Key Option for the 

    Reconstruction  Phase  after  War,  Creative  Construction  Conference  2017,  Procedia 

    Engineering  Volume  196,  Pages  211-219,  ISSN  1877-7058, 

    https://doi.org/10.1016/j.proeng.2017.08.074.

    [12]  Safour, R., Ahmed, S. & Zaarour, B., 2021. BIM Adoption around the World. International 

    Journal of BIM and Engineering Science, 4(2), pp. 49 -63. 

    [13]  Elhendawi, A., Omar, H., Elbeltagi, E. and Smith, A., 2019. Practical approach for paving the way 

    to  motivate  BIM  non-users  to  adopt  BIM. International  Journal  of  BIM  and  Engineering 

    Science, 2(2), pp.1-22.

    [14]  Evans,  M.,  Farrell,  P.,  Elbeltagi,  E.,  Mashali,  A.  and  Elhendawi,  A.,  2020.  Influence  of 

    partnering  agreements  associated  with  BIM  adoption  on  stakeholder's  behaviour  in 

    construction  mega-projects. International  Journal  of  BIM  and  Engineering  Science , 3(1), 

    pp.1-20.

    [15]  Elhendawi, A., Smith, A. and Elbeltagi,  E., 2019. Methodology for BIM  implementation in the 

    Kingdom of Saudi Arabia. International Journal of BIM and Engineering Science, 2(1).

    [16]  Ahmed,  S.,  Dlask,  P.,  Selim,  O.  and  Elhendawi,  A.,  2018.  BIM  Performance  Improvement 

    Framework  for  Syrian  AEC  Companies. International  Journal  of  BIM  and  Engineering 

    Science, 1(1), pp.21-41.

    Cite This Article As :
    Saada, Michel. , Aslan, Hala. The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war. International Journal of BIM and Engineering Science, vol. , no. , 2022, pp. 08-18. DOI: https://doi.org/10.54216/IJBES.050201
    Saada, M. Aslan, H. (2022). The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war. International Journal of BIM and Engineering Science, (), 08-18. DOI: https://doi.org/10.54216/IJBES.050201
    Saada, Michel. Aslan, Hala. The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war. International Journal of BIM and Engineering Science , no. (2022): 08-18. DOI: https://doi.org/10.54216/IJBES.050201
    Saada, M. , Aslan, H. (2022) . The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war. International Journal of BIM and Engineering Science , () , 08-18 . DOI: https://doi.org/10.54216/IJBES.050201
    Saada M. , Aslan H. [2022]. The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war. International Journal of BIM and Engineering Science. (): 08-18. DOI: https://doi.org/10.54216/IJBES.050201
    Saada, M. Aslan, H. "The effectiveness of applying BIM in increasing the accuracy of estimating quantities for public facilities rehabilitation projects in Syria after the war," International Journal of BIM and Engineering Science, vol. , no. , pp. 08-18, 2022. DOI: https://doi.org/10.54216/IJBES.050201